DRAINAGE WORKS IMPLEMENTED AND IN PROGRESS FOR THE 2007 MAY/JUNE

 

 

 

Description of Works

 

Status

 

Cost G$

 

 

Region No. 2

 

 

1

Construction of Drainage Sluice at Charity, Essequibo.

Completed

36.0

2

Installation of New sluice door at Windsor Castle.

Completed.

1.0

3

Servicing of Drainage pumps.

Completed

0.5

4

Construction of New Sluice door at Three Friends, Essequibo.

Completed

1.2

 

 

Region No. 3

 

 

5

Manual of Cleaning of Canal No. 1 and No. 2

In progress

1.0

6

Maintenance of 13,00 rods of canals within the Vreed-En-Hoop La Jalousie Water Users Association Area

On-going

4.0

7

Maintenance of 1300 rods of canals within Vergenoegen/Naamryck Water Users Area.

On-going

7.0

8

Construction of Drainage Structure at Leguan Island.

In Progress

10.0

9

Installation of Winch at Canefield Leguan Island.

In Progress

1.5

10

Installation of HDPE tube culvert at Palmyra Wakenaam.

Completed

0.5

11

Construction of Revetment at Warami, Boresarie Conservancy

Completed

7.0

 

 

Region No. 4

 

 

12

Mechanical cleaning of Craig Milne/Victoria Drainage canal

Completed

1.0

131

Mechanical Cleaning of Belfield Main Drainage Canal

Completed

1.0

4

Replacement of Power Cable on the # 1 Victoria pump.

Completed

6.5

15

Maintenance of 33,600 rods of canals in the Cane Grove Water Users Association Area.

On-going

9.3

16

Maintenance of 18,500 rods of canals in the Golden Grove/Victoria Water Users Association Area.

On-going

4.4

17

Maintenance of 28,000 rods of canals in the Ann’s Grove/Two Friends, Dutch Four CDC Area.

On-going

6.7

18

Maintenance of 23,000 rods of canals within the Hope Coconut Industries Area.

On-going

5.5

19

Maintenance of 5,500 rods of canals within the Belfield CDC Area.

On-going

1.3

20

Maintenance of 7,300 rods of canals within the Cove and John CDC Area.

On-going

1.7

21

Maintenance of 9,500 rods of canals within the Haslington and Greenfield CDC areas.

On-going

2.2

22

Maintenance of 18,000 rods of canals within Friendship East Bank Demerara, areas.

On-going

4.3

23

Maintenance of 6000 rods of canals in Craig, East Bank Demerara.

On-going

1.4

24

Jetting of Greenfield Sluice Outfall Channel

Completed

0.5

25

Installation of Mobile Pump at Hope Sluice Outfall Channel.

Completed

0.4

26

Repairs to Lilladrie Sluice, Friendship, East Bank Demerara

Completed

0.5

 

 

Region No. 5

 

 

27

Construction of Revetment and desilting of Bellamy Sluice inlet and Outlet Channel.

Completed

23.0

28

Spraying of weeds in Mahaicony Creek.

Completed

1.5

 

MMA/ADA

 

 

29

Rehabilitation of 90 miles of secondary canals within the MMA area has commenced.

In Progress

25.0

30

Maintenance of the Primary system canals.

Completed

30.0

31

Repairs to Hypark sluice.

Completed

2.0

32

Maintenance of Sluice structures along the Right Bank of the Abary River.

Completed

2.0

 

 

Region No. 6

 

 

33

Cleaning and Excavation of Busslelust Drainage Canal.

Completed

1.4

34

Excavate whim Drainage Canal

Completed

1.2

35

Excavation of Drainage Canal in Kokriete Savannah

Completed

9.5

36

Excavation of No. 51-52 outfall channel.

Completed

1.0

37

Maintenance of No. 66 Creek

On-Going

1.0

38

Maintenance of No. 52/74 Façade Drain

Completed

1.2

39

Maintenance of Crabwood Creek Façade Drain

On-going

0.5

40

Maintenance of 18,000 rods of canals and drains within Black Bush Polder Water Users Area.

On-going

7.0

41

Maintenance of 65,400 rods of drains and canals within No’s 52/74 Water Users Area.

On-going

9.0

41

Maintenance of 10,000 rods of canals and drains within Crabwood Creek Water users Area.

On-going

4.5

 

 

Region No. 10

 

 

42

Construct Revetment at Catiburi embankment.

In progress

0.5

43

Maintenance of Ice water creek

Completed

1.8

44

Desilting of Kaka Kara River mouth

In Progress

1.0

45

Cleaning of Drains in West Watooka, Industrial Area, Poker Street, Kara Kara, Blue Berry Hill, Silvercity.

To Commence in the Coming week.

10.0

 

 

East Demerara Water Conservancy

 

 

46

Repairs to Kofi Relief Channel Embankment

In progress

12.0

47

Maintenance of Water ways within the EDWC

On Going

1.0

 

Total Cost

 

 

262.5

 

 

Item No

Description of Works

Status

Cost G$

1.0

Excavation of Drainage Channel in Melanie/ Enterprise.

Completed

1.5 M

2.0

Cleaning of drainage canal in LBI

Completed

0.5 M

3.0

Cleaning of Drainage channel at Friendship/Elsie.

To commence on Thursday, 24, 2007

0.4 M

4.0

Cleaning of Canal No. 1 and No. 2 main drain.

Completed

0.6 M

5.0

Cleaning of internal drains and outlet in Bell West.

In Progress.

0.4 M

6.0

Cleaning of drains and canals in Region No. 10

To commence by Monday, 28, 2007

25.0 M

7.0

Cleaning of main drain in Enterprise.

Completed

0.6 M

 

Award of Contracts

 

 

8.0

Supply and Installation of 2 large Hydraulically Driven Drainage Pumps in Region No. 3 and 4

Awarded

86.0 M

 

Total

 

115.0 M

 

 

 

Total Cost: G$ 377.5 M

 

 

 

 

 

 

 